To minimize traffic and delays, this project
is intended for mostly nighttime work, however, with the approval
of the Engineer, work may be allowed during the weekday (Monday
through Friday), during the hours of 9:00 a.m. to 3:00 p.m. (Daytime
work is limited to off the roadway and/or shoulder closures and
the work will not adversely affect traffic.)
Activity on the project will be restricted according to the following
work schedule: All work on the travel lanes of Route I-495 is restricted
to the hours of 9:00 p.m. Sunday to 5:00 a.m. Monday and 9:00 p.m.
to 5:00 am.m. for all shifts commencing Monday through Thursday
(for this week's schedule see above, left).
The work schedule may be altered on specific Sunday evening during
the summer months due to extreme high volumes of traffic. The alteration
will typically consist of an 11:00 p.m. Sunday evening start time
or as directed.
|